WKN Windpark Malarberget in Schweden

Wind farm Målarberget

Second sales success in Sweden for PNE Group

  • MW realised: 113 MW
  • Turbines erected: 27 WTG
  • Start of construction: June 2019

The "Målarberget" wind farm is located approximately 150 kilometres north-west of Stockholm; on completion, it will encompass 27 four-megawatt class wind power turbines. Construction of the wind farm began in the middle of 2019. It is expected that the wind farm will be commissioned in 2021. Moreover, the PNE Group will be responsible for the technical and commercial management of the wind farm after its completion.

The project was developed by WKN’s Swedish subsidiary VKS Vindkraft Sverige AB, which will also be building the wind farm for the buyer. WKN was also responsible for the sales process and sold the project rights to the Israeli company Enlight Renewable Energy.

back

country flag il
anfuehrungszeichen_rund

We are very happy about our first project in Sweden. This investment is part of Enlight's strategy to expand its activities into subsidy-free electricity markets. We are pleased to have found the WKN team to be a dedicated and professional project developer which shares our common vision and values as regards the global energy revolution.

Gilad Yavetz, CEO, Enlight Renewable Energy LTD

to the top